Share What we showed you in August 2024 on Facebook
Share What we showed you in August 2024 on Linkedin
Email What we showed you in August 2024 link
Update August 2024
Following a detailed redesign of the proposals during 2024, to incorporate the governments building safety regulation changes and a stand-alone community centre and mosque, the council’s Development Committee gave their support to the application on the 12th June, recommending that planning permission be granted. This was a key milestone to cross and our thanks go to PRP Architects for all their hard work to get the application submitted on target.
Selection of a developer partner
In March 2024 the process began to select a preferred developer partner to work with us to price and deliver the construction stage of this project. This procurement process is an exercise of tendering (advertising and requesting bids), evaluating and appointing a chosen developer to work with the council. The council allowed eight weeks for potential contractors to return their bids. However bidders asked us for another four weeks to complete this bids before submitting these to the council. The closing date for the council to receive the bids was the 26th June.
The council is now in the process of clarifying and evaluating the bids. This means that the project team and other relevant teams in the council, such as finance and legal colleagues look at the content of the bids and engage in dialogue with the bidders to explore the detail of their proposals, before scoring each bidders submission. As always your Residents’ Panel has been involved along the way and the Panel chose two representatives to form part of the evaluation panel scoring the non-commercial elements of the bids. Our thanks to Robi and Eric for giving up their time so generously. Once the council has completed the evaluation process, it will appoint the highest scoring organisation, we expect this to take place in September. However, before the winning bidder can be announced publicly, there will be a period of commercial negotiation over the contract, followed by a mandatory 2 week ‘stand still period’ when all bidders are informed of the outcome and can raise any queries they may have. Hopefully an announcement will be possible in late October, but we’ll be intouch as soon as we’re able.
Buy-Backs update & selling your home back to the council
The leasehold buyback scheme is fully under way with nine resident and non-resident leasehold buybacks already complete. There are many more in the pipeline going through the selling process. As always please do make use of the Rehousing Guides which can be found within the Rehousing Documents section of this page. It is also worth keeping the details of JLL (the council’s appointed valuer) at hand for when you are ready to have your property valued: contact Tim Surry on 07548 099 645 or email tim.surry@jll.com
*To view a larger image of the timeline, please right click on image and select magnify image.
____________________________________________________________________________
Planning Application
The Council’s Development Committee passed a resolution to award planning consent for regeneration to proceed on 21st March 2022, subject to confirmation by Greater London Authority (GLA).
The planning reference for this application is PA/21/02703 should you wish to view the planning application and associated documents on the council's planning portal.
Rehousing Documents
Following a series of tenure specific consultation workshops held in December 2020, please view the document section to view the tenure specific rehousing guides. If you have any questions on these, please contact a member of the team by emailing clichyestate@towerhamlets.gov.uk
Share What we showed you in February & March 2024 on Facebook
Share What we showed you in February & March 2024 on Linkedin
Email What we showed you in February & March 2024 link
Update March 2024
Revised planning application submitted
We are pleased to announce that a revised application for the HAP Regeneration Scheme was submitted to the Local Planning Authority on 1st March 2024. If you would like to view the planning application and any of its associated documents, its reference number is PA/24/00368. The planning portal can be accessed via the council’s planning portal using this weblink https://development.towerhamlets.gov.uk/online-applications/
Since June 2023 we have begun buying back properties on the estate from those wishing to sell their property and move/invest elsewhere. To date 5 completions have taken place and 10 cases are going through the selling process. These flats will not be left empty but used in the meantime as temporary accommodation for households currently in less suitable and more expensive temporary accommodation.
Rehousing drop-in sessions (date for your diary!)
The team are aware that while plenty of residents are eager to engage in the rehousing process, many residents feel some concern about this area, given all the different aspects to think about. To try and assist you, the council is hosting two re-housing drop-in sessions where officers will be availabe for you to come and discuss your rehousing. Secure tenants will be able to talk to staff from the Lettings Team regarding decant status and their housing options. Resident and Non-resident leaseholders will be able to discuss any issues they have regarding valuation or compensation with JLL, the council’s valuers for this project. Members of the Project Team will also be in attendance to discuss any other re-housing matters.
Dates: Tuesday 16 April from 1PM - 5PM & Thursday 18 April from 4PM - 7PM
Venue: 262 Stepney Way (Redcoat building next door to the mosque)
Selling Your Property to the Council
If you are a leaseholder and have yet to have your property surveyed for the purpose of selling your home, then please contact JLL, so they can visit you and carry out a valuation. This an important step, even if you are intending to remain on the estate in one of the newly build homes. You can contact JLL by calling Tim Surry on 07548 099 645 or email tim.surry@jll.com
A New Development Partner
The council has started the process of selecting a developer partner and this work will increase in the coming months. Two members of the Residents’ Panel have volunteered to help in the selection process. Once a developer is chosen it will be announced in the summer newsletter along with an updated timeline for the scheme.
What we showed you in February 2024
In our last public consultation, we brought you the below material.
https://talk.towerhamlets.gov.uk/5813/widgets/90348/documents/56444
Updated Buy-Back Guides
We have now updated our buy-back guides and copies of these can be found within the Documents section of this page. The new updated guides are for Resident and Non-resident Leaseholders. The buy-back process has commenced and the Council has appointed JLL as the Valuers for your property. Please contact JLL directly, who have written to you separately, with any queries.
Programme
Harriott, Apsley, Pattison Houses - Newsletter December 2022
This year has been one of change in Tower Hamlets with the election of a new Mayor and administration which brought some new councillors and Cabinet members on board who are also keen to deliver much needed new housing in the borough. It may not feel like there has been a lot going on, but behind the scenes the team has been progressing towards securing full planning approval, bringing the newly elected Mayor up to date on scheme progress and considering alternative designs for the mosque and community centre.
Residents Panel
The Residents’ Panel has remained engaged throughout the past year, with meetings in January, May, June, September and November. They have worked hard on behalf of residents by providing useful feedback to the project team on communications with the community as well as informing officers of feelings on the estate during the ups and downs of the last year. The project team heard from the Panel about their concerns regarding the recent delay to securing planning permission and officers are pushing hard to see this confirmed in the early part of 2023.
Looking ahead to 2023
Leaseholders will be contacted in January to announce the launch of the buy-back package in February and the commencement of voluntary negotiations to acquire homes on the estate, particularly for those not wishing/eligible to take-up one of the new homes to be built. An external valuer is currently being appointed and this process is expected to be finished in January 2023; this will enable individual meetings to start with leaseholders on the valuation of their properties. For further background information on the rehousing/buy-back programme please see the ‘Key Documents’ section of the scheme’s webpage using the link below. We will be writing to you closer to the time to confirm the start of the buy-back programme and providing full details.
Upon confirmation of the planning decision in 2023, the project will move into another new phase, when we will be able to launch the rehousing programme for secure tenants. Decant status has already been approved in principle by the Common Housing Register Forum and will go live once all planning approvals are agreed between the Council and the Greater London Authority (GLA). Once the council has the seal of approval from the GLA, colleagues in the Housing Options Team will start their liaison with tenants to discuss individual decant options.
Share Why does the Council need to build more homes? on Facebook
Share Why does the Council need to build more homes? on Linkedin
Email Why does the Council need to build more homes? link
The average cost of renting a flat in Tower Hamlets is now more than the average household income. There are already more than 19,000 households on the housing register in need of an affordable home and more than 2,000 households are living in temporary accommodation. Although more new homes were built in Tower Hamlets in 2018 than anywhere else in the UK, the average price is now 22 times the average salary, so our residents often can’t afford to buy them.
In response, the council has committed to delivering 2,000 new council homes. These genuinely affordable homes will include properties big enough for families. One in ten will be wheelchair accessible.
At just eight square miles, space to build in Tower Hamlets is in short supply. We’re making the most of land that we already own, including buildings no longer used as they once were.
But that isn’t enough. We also need to look closely at whether there is room for us to increase the number of homes on existing estates.
We can do this by finding ‘infill sites’ or gaps on estates where new buildings can go. We’re also looking carefully to see if we can redevelop existing estates to replace older buildings with ones that are modern, better designed and crucially, that provide more council homes for our residents.
Read next: why Harriott,Apsley and Pattison (HAP) houses
Share Why Harriott, Apsley and Pattison (HAP) Houses? on Facebook
Share Why Harriott, Apsley and Pattison (HAP) Houses? on Linkedin
Email Why Harriott, Apsley and Pattison (HAP) Houses? link
We have looked closely at all the estates across the borough to identify where there is the best opportunity to increase the amount of council housing. We found that not only does the area around Harriott, Apsley and Pattison (HAP) Houses have room to accommodate new homes, there will be space for a new mosque and improved open spaces.
Read next: Our promise to residents
Take survey
Share Our promise to residents on Facebook
Share Our promise to residents on Linkedin
Email Our promise to residents link
- We will keep the community together.
- More council homes for social rent.
- Reduced crime and anti-social behaviour through better design.
- New homes at social rents for all existing council tenants.
- Options to suit every leaseholder.
- Addressing overcrowding on the estate through the provision of new affordable homes.
- One move to a new home, wherever possible.
- Financial compensation and all reasonable moving costs paid.
- Current street parking permits guaranteed.
- Residents’ Panel representing residents in decision making and shaping the future of their estate.
- Door-to-door moving support for older and vulnerable residents.
Read next: Design principles for the new development
Take survey
Share Design principles for the new development on Facebook
Share Design principles for the new development on Linkedin
Email Design principles for the new development link
The council is committed to providing high quality, well designed homes and surroundings to create healthy and sustainable environments where people want to live. We will deliver a mix of home sizes to meet the local housing need, with a combination of flats and duplexes and a mix of tenures for families with children and for small and single person households.
Landscaped spaces will include trees, planting, grassed areas and children’s play areas. Biodiversity will be key in planning planting, buildings will be laid out to maximise daylight and sunlight, while homes will be energy efficient. Developments will be well connected, with safe and active streets designed to reduce antisocial behaviour. We will enhance and continue to build a strong sense of community and belonging in any development.
Read next: What regeneration will deliver
Take survey
Share What regeneration will deliver on Facebook
Share What regeneration will deliver on Linkedin
Email What regeneration will deliver link
A mixed, cohesive and sustainable community.
Good quality and well-designed homes that will meet residents housing needs.
More social rented homes.
More family sized homes.
Private amenity space to all properties with a gap between homes and public areas to provide privacy for ground floor properties.
Safer streets and homes through good design and improved lighting.
New, usable communal areas creating attractive green spaces for residents.
Energy efficient homes.
Homes built to minimise noise nuisance.
Improved and secure provision for bins and bike stores.
Maximised green space by keeping car use to a minimum.
A home adapted to your needs, if you have a disability.
All homes will benefit from at least the national standard required for storage.
Family units with three or more bedrooms will have separate kitchens.
Wherever possible, two bedroom homes will have options for separate or open plan kitchens and living space.