Liveable Streets Bethnal Green

Share on Facebook Share on Twitter Share on Linkedin Email this link

Liveable Streets is a multi-million-pound borough-wide street and public space improvement programme. It aims to improve the look and feel of public spaces in neighbourhoods across the borough and make it easier, safer, and more convenient to get around by foot, bike and public transport.

Please refer to the right side of the page to find out more about the previous stages of the Liveable Streets Bethnal Green programme and engagement activities.


UPDATE 25 November 2020: Gosset Street/Columbia Road Detailed Design

The improvements to the Gosset Street area form a key part of the Liveable Streets programme and we want the public realm design to enhance the area as best as possible. As the final stages of the Gosset Street engagement process have taken place during the Covid-19 restrictions, engagement with residents in the area has been held online via webinar format.

Thank you to all contributors for their ideas so far and, as we are now reaching the end stage of the detailed design, we would like to get final comments from the wider community on these design proposals.

We are enthusiastic to hear your ideas so please visit the Gosset Street project page for more details.


Bethnal Green Construction

Construction phases

The programme is now moving into the construction phase for the Bethnal Green area. We will update each neighbourhood on the specific works taking place on the roads around them, or you can see the below timeline for when a scheme area near you is scheduled to commence construction.

Click here to see all the changes to the road layout across the Bethnal Green area. The full range of improvements will be detailed below.

Construction updates

Works are currently progressing on Old Bethnal Green Road (Scheme 4) and will be completed in stages to minimise any disruption. The update below shows the current status of the Old Bethnal Green Road works.

Old Bethnal Green Road, images of current ongoing work. Click to enlarge image.

To find out more about Scheme 4 works, please see the notification letter for residents.

You can also view the work commencement letters that have been distributed to all affected areas.


Works are also progressing along Clarkson Street, Middleton Street, Punderson's Gardens and Clare Street. A breakdown of the works can be found in the below table.

Work statusLocationWork Type
Work progressing as plannedClarkson Street
  • Work to create no through route for vehicles along Clarkson Street. Closure at the corner of Middleton Green with no longer having access to Ellsworth Street
  • Installation of road closure points
  • Some mechanical excavators will be used during these works
TBCMiddleton Street
  • Footway improvements and buildout
  • Installation of traffic calming speed hump
Work progressing as planned
Punderson's Gardens
  • Works to create no through route for vehicles along Punderson's Gardens from Middleton Street to Bethnal Green Road
  • Some mechanical excavators will be used during these works
On Hold until 2021Clare Street
  • Work to create no through route for vehicles along Clare Street from Hackney Road to Old Bethnal Green Road
  • Some mechanical excavators will be used during these works


Clarkson Street, as shown below, is progressing as planned and is in the final stages of construction. We expect this to be completed in the coming weeks.

Clarkson Street, images of current ongoing work. Click to enlarge image.

Punderson's Gardens, like Clarkson street, is also progressing on track with construction nearing to an end. We expect this to be completed imminently within the coming weeks.

Punderson's Gardens, images of current ongoing work. Click to enlarge image.


Coronavirus updates

Our Liveable Streets programme team are following government advice and are currently working remotely. Work will continue as planned on the projects and the team will adhere to all guidelines.

Please note construction timing is subject to change depending on changes to coronavirus restrictions, weather and coordination of works in the area. We will update the website with any changes to the programme and hope you will continue to help us improve the look and feel of your neighbourhood.

For coronavirus updates from Tower Hamlets or to join our mailing list please click here.

Contact us

If you have any questions regarding the construction phase please see below, or get in touch with the team by emailing liveablestreets@towerhamlets.gov.uk or calling 0203 092 0401.

Liveable Streets is a multi-million-pound borough-wide street and public space improvement programme. It aims to improve the look and feel of public spaces in neighbourhoods across the borough and make it easier, safer, and more convenient to get around by foot, bike and public transport.

Please refer to the right side of the page to find out more about the previous stages of the Liveable Streets Bethnal Green programme and engagement activities.


UPDATE 25 November 2020: Gosset Street/Columbia Road Detailed Design

The improvements to the Gosset Street area form a key part of the Liveable Streets programme and we want the public realm design to enhance the area as best as possible. As the final stages of the Gosset Street engagement process have taken place during the Covid-19 restrictions, engagement with residents in the area has been held online via webinar format.

Thank you to all contributors for their ideas so far and, as we are now reaching the end stage of the detailed design, we would like to get final comments from the wider community on these design proposals.

We are enthusiastic to hear your ideas so please visit the Gosset Street project page for more details.


Bethnal Green Construction

Construction phases

The programme is now moving into the construction phase for the Bethnal Green area. We will update each neighbourhood on the specific works taking place on the roads around them, or you can see the below timeline for when a scheme area near you is scheduled to commence construction.

Click here to see all the changes to the road layout across the Bethnal Green area. The full range of improvements will be detailed below.

Construction updates

Works are currently progressing on Old Bethnal Green Road (Scheme 4) and will be completed in stages to minimise any disruption. The update below shows the current status of the Old Bethnal Green Road works.

Old Bethnal Green Road, images of current ongoing work. Click to enlarge image.

To find out more about Scheme 4 works, please see the notification letter for residents.

You can also view the work commencement letters that have been distributed to all affected areas.


Works are also progressing along Clarkson Street, Middleton Street, Punderson's Gardens and Clare Street. A breakdown of the works can be found in the below table.

Work statusLocationWork Type
Work progressing as plannedClarkson Street
  • Work to create no through route for vehicles along Clarkson Street. Closure at the corner of Middleton Green with no longer having access to Ellsworth Street
  • Installation of road closure points
  • Some mechanical excavators will be used during these works
TBCMiddleton Street
  • Footway improvements and buildout
  • Installation of traffic calming speed hump
Work progressing as planned
Punderson's Gardens
  • Works to create no through route for vehicles along Punderson's Gardens from Middleton Street to Bethnal Green Road
  • Some mechanical excavators will be used during these works
On Hold until 2021Clare Street
  • Work to create no through route for vehicles along Clare Street from Hackney Road to Old Bethnal Green Road
  • Some mechanical excavators will be used during these works


Clarkson Street, as shown below, is progressing as planned and is in the final stages of construction. We expect this to be completed in the coming weeks.

Clarkson Street, images of current ongoing work. Click to enlarge image.

Punderson's Gardens, like Clarkson street, is also progressing on track with construction nearing to an end. We expect this to be completed imminently within the coming weeks.

Punderson's Gardens, images of current ongoing work. Click to enlarge image.


Coronavirus updates

Our Liveable Streets programme team are following government advice and are currently working remotely. Work will continue as planned on the projects and the team will adhere to all guidelines.

Please note construction timing is subject to change depending on changes to coronavirus restrictions, weather and coordination of works in the area. We will update the website with any changes to the programme and hope you will continue to help us improve the look and feel of your neighbourhood.

For coronavirus updates from Tower Hamlets or to join our mailing list please click here.

Contact us

If you have any questions regarding the construction phase please see below, or get in touch with the team by emailing liveablestreets@towerhamlets.gov.uk or calling 0203 092 0401.

Please submit any questions you have regarding the construction phase of Liveable Streets Bethnal Green. The team will aim to respond to you within a few business days.

Bethnal Green Construction Updates

loader image
Didn't receive confirmation?
Seems like you are already registered, please provide the password. Forgot your password? Create a new one now.
  • Share on Facebook Share on Twitter Share on Linkedin Email this link

    When will Warner place be implemented as a one way system? The noise from it being used as a rat run / cut through is becoming increasingly problematic - there are constant traffic blockages and fights and shouting and sounding of horns from idiot drivers

    Fed up asked 3 days ago

    Hello, 

    The Warner Place closure is currently under review by the council and has yet to be given a commencement date. The closure will now most likely take place early next year whilst we work to implement the School Streets closure along Pollard Row first. 


    Kind Regards,

    David

    The Liveable Streets Team

  • Share on Facebook Share on Twitter Share on Linkedin Email this link

    Hello Can you tell me when the closure on Pollard Row will be going in? there has been a huge increase in the amount of traffic using Pollard Row this week (possibly due to people avoiding the road works at the Hackney Road junction with Cambridge Heath Road), with traffic queuing back to Bethnal Green Road, impatient drivers honking horns, stationary cars blaring music etc. There have been many tipper trucks, concrete mixers and other large vehicles unsuitable for residential roads using Pollard Row as well. Please get the closure in as soon as possible to stop this happening. Thanks

    Ed asked 2 months ago

    Hello, 

    The Pollard road closure has been temporarily delayed until further notice. We will distribute commencement letters to the surrounding areas and update the website prior to any works occurring.

    Kind Regards, 

    David

    The Liveable Streets Team

  • Share on Facebook Share on Twitter Share on Linkedin Email this link

    Hi I wonder if you could help me understand the scheme a bit better. I understand that there are still two options being considered around the Jesus Green area. Option 1: being closures on both Barnet Grove and Durant street and option 2: being closures on both Wellington row and Barney Grove at the junction of the two And closure of Quilter street at its junction with Ravenscroft street. I live on Elwin Street. With either of these two options and the other planned changes, the only way I can see that I will be able to drive to my house is from the Hackney Road only, via Shipton Street, then the top of Columbia road into Barnet Grove and finally into Elwin street. And that I will not have access to Elwin Street from the south ie From Bethnal Green Road. Please can you confirm that my understanding on these two points are correct. If this is the case then I cannot see how I can access my house by car on sundays as the Columbia Rd market usually blocks the top of Columbia road, or at at least makes it very difficult to get through. Many thanks

    Giff asked 5 months ago

    Hi Giff, 

    The extension of  Columbia market is only temporary in order to allow traders to adhere to social distancing. As it is only a temporary measure you will regain access to Barnet Grove Road via Columbia Road in the future before any final decision is made. We understand that if this was to progress with the extension of the market then there would be no way to access your road via vehicle and this Is not what the plans intend. 

    In regards to the closures. I believe you are correct and this would be the case that you would access your road via Hackney Road and Shipton Street and that access via the South will be blocked.  

    Kind Regards, 

    The Liveable Streets Team


  • Share on Facebook Share on Twitter Share on Linkedin Email this link

    As you know, there have been significant changes to the Market layout to facilitate social distancing, which appear to be working very well. As far as I can see, both of the options for Barnet Grove assume the original Market arrangements. Is there going to be an opportunity to revisit the closure location if you decide to retain the new Market layout? I would have thought that there was a strong case for reverting to the original proposal of a closure at the top of Barnet Grove if that is the case.

    ec1 asked 4 months ago

    Hello, 

    We are proceeding with the current consultation based on the premise that the market will not be remaining extended in future. There currently is no plan to revisit closure locations.

    However, if the market was decided to remain extended in future to maintain social distancing measures, then options 1 and 2 may no longer be viable options and will have to be reviewed based on the new circumstances presented. We will keep the community updated with the latest news based on the most current situation.

    Kind Regards,

    The Liveable Streets Team

  • Share on Facebook Share on Twitter Share on Linkedin Email this link

    The LBTH webpage for road closures states: Road closures are a means of stopping all through traffic. Roads are usually closed by a barrier, with an emergency access gate for emergency service vehicles. Where there is a road closure, a provision needs to be made for large vehicles to turn round. This is why roads are not generally closed in residential areas. Also road closures inconvenience residents as they make it more difficult for them to get to their homes. But now you re imposing these very same measures under your so-called Liveable Street program in narrow streets where there is not possibility of vehicles turning around.

    Wattle asked 4 months ago

    Hello, 

    A vehicle swept-path analysis was conducted to ensure that typical sized vehicles are able to turn around at the proposed road closure. No-through road signage will be displayed at junctions in advance, as part of the measures to inform motorists and discourage them from entering the roads unnecessarily.

    Kind Regards,

    The Liveable Streets Team

  • Share on Facebook Share on Twitter Share on Linkedin Email this link

    The map for the Barnet Grove survey is incomplete. It fails to show the entirety of the area impacted by closing Barnet Grove, what the possible access and exit point are, and makes no reference to the previously mapped one way streets. How is anyone supposed to understand the impact of the proposed changes. At the same time, the two options on offer only make a real difference to some 75 houses, primarily on Quilter Street. This is not offering residents any real option at all.

    Wattle asked 4 months ago

    Hello, 

    Please refer to the Bethnal Green wider plan linked below. This provides a larger plan of all works going on across the area. 

    https://talk.towerhamlets.gov.uk/4093/widgets/12671/documents/4864

    To voice your opinion on the options please make sure to fill out the online survey so we can review your comments. 

    https://talk.towerhamlets.gov.uk/lsbethnalgreen/survey_tools/poll1 

    Kind Regards, 

    The Liveable Streets Team

  • Share on Facebook Share on Twitter Share on Linkedin Email this link

    Could you please list the residential roads in the Jesus Green area which have had consultation forms regarding the most recent Barnet Grove options. Would be useful to know as some residents have not received consultation forms, but they may fall outside of the consultation area. Important to know asap with the deadline approaching. Thank you

    NWF asked 4 months ago

    Hello, 

    Our consultation document below provides a clear redline boundary around the project area. Every road within this area would have received a consultation document. 

    https://talk.towerhamlets.gov.uk/4093/widgets/12671/documents/5391 

    For further reference, I have also outlined the roads below that would have received documents:

    • Columbia Road 
    • Barnet Grove 
    • Quilter Street 
    • Elwin Street 
    • Ravenscroft Street 
    • Wellington Row 
    • Gosset Street 
    • Delta Street  
    • The Way 
    • Wimbolt Street  
    • Baxendale Street 
    • Durant Street 
    • Ropley Street 
    • Ezra Street 
    • Shipton Street 
    • Horatio Street  


    Kind Regards, 

    The Liveable Streets Team

  • Share on Facebook Share on Twitter Share on Linkedin Email this link

    When is the road closure between Clarkson Street and around Ellsworth Street estimated to be active?

    AndyT asked 4 months ago

    Hello, 


    The road closure between Clarkson Street and Ellsworth Street is yet to come into force. Construction work began on old Bethnal Green Road on Friday 12th June after the easing of lockdown measures due to COVID-19. Once these are completed, the next stage of the construction works will include implementing a road closure between Clarkson Street and Ellsworth Street. We will notify properties in the area ahead of expected works taking place near them.   

    Kind Regards, 

    The Liveable Streets Team

  • Share on Facebook Share on Twitter Share on Linkedin Email this link

    hello Liveable Streets Team, Please can you give an an assurance that you are committed to the residents on the Boundary Estate and the residential nature of the area by clearly stating that (1) you are not having any street trading permitted within the Boundary Estate demise at any time. (2) that no more alcohol on or off licences will be issued with in this same area (3) that you share you plans for policing any anti social behaviour that will result from the change in use from roads to pedestrian access only. The last point is in light of the current unrestricted car bar , gas station, drug stores that are currently allowed to operate unchecked, and which cause aggravation to residents. Many thanks, David

    DavidM asked 4 months ago

    Hello David, 

    We are not proposing any changes to licensing in the Arnold Circus area. Please note that we are not directly responsible for the licensing of the area. This responsibility falls to the Tower Hamlets licensing team that issues them. 

    In reference to policing. Although the Tower Hamlets Liveable Streets Team liaises with the police and safer neighborhoods team, we do not create plans for their policing. It is ultimately down to the police and safer neighborhoods team to address these anti-social issues presented. 

    Many issues associated with Arnold Circus are due to vehicles parking there and we anticipate volumes of this activity to decline as the majority of the circle will be closed to vehicle traffic. 

    Kind Regards, 

    The Liveable Streets Team

  • Share on Facebook Share on Twitter Share on Linkedin Email this link

    I write this on behalf of my 84 year old parents living in Durant Street. They are very worried and concerned that they may not be able to get out in their car now as they cannot work out on the small map you sent them how they would do so. They are also scared that they now cant have visitors. He has lived in the same house for 84 years and says this is the first time in his life he is not free to come and go.

    ronhunt asked 5 months ago

    Hello, 

    All areas will still be accessible by car. There will be no loss of parking so there will be no change to available parking for visitors etc in the area. If you like please email www.towerhamlets.gov.uk/liveablestreets with your parent's address and we would be happy to send a larger version of the plan over to them. 

    Kind Regards,

    The Liveable Streets Team